CEQA Litigation Win

EIR

RJR Attorneys Successfully Defend 180-Unit Housing Development

Earlier this month, the First District Court of Appeals handed down a win for our client in a CEQA lawsuit challenging the approval of a 180-unit residential project in Petaluma (Project). (Save North Petaluma River and Wetlands v. City of Petaluma (Nov. 14, 2022, A163192) [nonpub. opn.].) Matthew Visick and Sabrina Eshaghi of our office represented the developer during entitlements and litigation.

The Court confirmed:

  • The “baseline” conditions against which biological impacts are measured can be drawn from site visits, studies, and habitat evaluations that were undertaken both before and after the Notice of Preparation (NOP) for the Environmental Impact Report (EIR) is issued; and
  • The EIR need not contain a standalone analysis of evacuation impacts, despite expert testimony to the contrary, where substantial evidence indicates large-scale evacuations would not be necessary.

The Project went through an extensive environmental review process that resulted in the release of a Draft EIR in 2018. The City allowed for an extended public comment period on the Draft EIR and held two hearings to solicit additional comments before preparing the Final EIR. As intended under CEQA, the developer adjusted the project multiple times to respond to comments received during the hearings on the Draft and Final EIR. Despite the developer’s efforts to respond to community input, opponents of the Project submitted a letter from an attorney to the City on the day the City Council approved the Project asserting a broad range of alleged errors in the Project’s CEQA review. Soon after the City Council approved the Project, the opponents filed a lawsuit seeking to invalidate the approval.

At the Trial Court, in addition to challenging the adequacy of the EIR’s biological resources and emergency evacuation analysis, the opponents claimed the developer had deprived the public of its right to meaningfully participate in the CEQA process by making changes to the Project in response to public and City input after publication of the Final EIR, failed to analyze the impact of formaldehyde off gassing from composite building products, and failed to adequately analyze potential impacts related to flooding from the adjacent Petaluma River. The Trial Court rejected the opponents’ wide-ranging claims and upheld the EIR’s certification. The opponents promptly appealed.

The Court of Appeal affirmed the Trial Court’s decision as to the two issues raised on appeal: the “baseline” for measuring biological resources impacts and the adequacy of the Project’s emergency evacuation analysis.

First, the Court agreed that information and analysis conducted both before and after the NOP is issued can be the basis for establishing the “baseline” against which Project impacts are measured. The state CEQA Guidelines generally require existing baseline conditions to be based on the environmental conditions at the time the NOP issues. Here, the NOP was published in 2007, but a special status species report for the EIR’s biological resources analysis was drafted in 2004. The EIR indicated its analysis included updated database reviews and information gathered from site visits in the years following the NOP. The Court confirmed that the use of materials from before and after the NOP issued did not require additional justification because there was no indication that the conditions had changed. Instead, the Court determined that the “inclusion of the post-2007 information indicates that the EIR was prepared with an eye toward ‘completeness’ and ‘a good faith effort at full disclosure.’” The Court also rejected the opponents’ argument that the EIR must provide additional documentation from the biologist’s studies and site visits to allow the opponents to evaluate whether they support the analysis in the EIR, confirming that factual information in the EIR itself may constitute substantial evidence. The Court also noted that the opponents could have obtained this information if they had raised their comments during the public comment period rather than on the day the Project was approved.

Second, the Court agreed that where the City has substantial evidence that large scale evaluations will not be necessary, the EIR need not include a stand alone analysis of evacuation impacts. While the EIR did include an analysis of the Project’s impact on adopted emergency response and evacuation plans, the opponents argued that the EIR also needed to evaluate egress and evacuation safety due to neighborhood concerns regarding flooding and grass fires as well as a letter from a “national evacuation expert” opining on allegedly dangerous public safety impacts in the event of an evacuation. The Court reaffirmed that CEQA does not allow courts to reweigh conflicting evidence when reviewing an EIR and that case law allowed the City to rely on the expertise of its staff to determine that the Project will not have a significant impact. Here, City staff prepared a memo reiterating that the Project is outside the 100-year floodplain and is not within the high fire severity zone, and the Assistant Fire Chief confirmed the Fire Department did not have significant flood or fire access/egress concerns. Given the analysis in the EIR and the corroborating statements from City staff, the Court concluded that the opponents failed to prove any inadequacy of the public safety analysis in the EIR.

This opinion affirms the deferential review that the Courts will give to an EIR. So long as the EIR reasonably sets forth enough information to allow informed public participation and allows the City to make a reasoned decision whether to approve a project, the Courts will not second guess the City’s decision to approve a project.

 

Authored by Reuben, Junius & Rose, LLP Attorney Sabrina Eshaghi.

The issues discussed in this update are not intended to be legal advice and no attorney-client relationship is established with the recipient.  Readers should consult with legal counsel before relying on any of the information contained herein.  Reuben, Junius & Rose, LLP is a full service real estate law firm.  We specialize in land use, development and entitlement law.  We also provide a wide range of transactional services, including leasing, acquisitions and sales, formation of limited liability companies and other entities, lending/workout assistance, subdivision and condominium work.

Density Bonus Law & CEQA Tiering Upheld

DBL

This winter, two California Courts of Appeal issued decisions that reaffirm some of the positive aspects of state laws related to housing production, from both a CEQA perspective and via the State Density Bonus Law (“DBL”). In the first case, out of East Bay city Newark, the First District Court of Appeal upheld a tiered CEQA review for a 469-lot subdivision based on a program-level EIR prepared for a Specific Plan. About a week later, the Fourth Appellate District upheld San Diego’s approval of a 20-story residential tower, relying heavily on the protections afforded to mixed-income residential projects under the DBL. We discuss each below.

In Newark, the City approved a specific plan in 2010 for up to 1,260 units, as well as a golf course and related facilities, relying on an EIR. The EIR specifically noted that Newark would proceed under CEQA Guidelines Section 15168 for specific development proposals and “tier” off of the EIR to the extent applicable. In 2019, the applicants submitted a subdivision map proposing 469 residential lots, but no golf course. Other changes from the development analyzed in the EIR included filling and elevating only certain areas on the site (the project site is located next to the San Francisco Bay) and locating the filled and elevated areas directly next to wetlands, with riprap along the western banks. The City prepared an exemption checklist comparing the EIR to the subdivision’s impacts and conducted background technical studies, including an updated sea level rise analysis. The checklist found that the subdivision would be consistent with the specific plan, and that there were no changed circumstances or new information that might trigger the need for more CEQA review than what was done for the EIR. It was a classic example of CEQA “tiering.”

The Court of Appeal upheld the City’s use of the checklist. First, it rejected an argument that the project changes made tiering inappropriate. The Court helpfully pointed out that changes in and of themselves do not eliminate the ability to tier off an EIR; instead, the environmental consequences resulting from those changes must be new, greater, or substantially different than what was analyzed in the EIR. Here, they were not. The Court also rejected the appellant’s claim that the amount and rate of sea level rise was different enough to require a new EIR, finding that the EIR’s unambiguous finding of a significant impact due to sea level rise was adequate, as was some language in the EIR noting that the rate of sea level rise was uncertain and might be accelerating.

Finally, the Court determined that adaptive management plans for sea level rise do not improperly defer consideration of mitigation measures. Taking a refreshingly common-sense approach to climate change and CEQA, the Court would not fault Newark for acknowledging in the EIR that adaptive management would be required. “The City’s potential responses to environmental conditions between 50 and 80 years from now cannot be considered part of the project,” it concluded. “Because the City currently can only dimly guess what measures will be needed to respond to conditions several generations from now, the City was not required to analyze the impacts of the adaptive pathways” as part of the project.

The Court of Appeal’s opinion in San Diego generated more buzz, particularly among the pro-housing groups that have done yeoman’s work in recent years to strengthen California’s housing protections. The case was originally not certified for publication, in part because San Diego’s City Attorney was reluctant to have a published case that so clearly spelled out the limits of the City’s discretion to deny or downsize density bonus projects. Nevertheless, after receiving petitions to publish it, the Court did. It is helpful in several ways, reaffirming the City’s evidentiary burden to deny waivers or concessions; harmonizing General Plan consistency findings with the DBL; and applying the conclusion the First District Court of Appeal reached in Wollmer v. City of Berkeley that a density bonus project can be approved with residential amenities such as a courtyard.

The Project—a 20-story, 204-unit mixed use tower at 6th Avenue and Olive Street across from Balboa Park—faced pushback from neighbors, at least some of whom the Court implied would lose their view of the park. Somewhat surprisingly, instead of arguing that the project would have an unmitigable health and safety impact on the adjacent park, the neighbors argued administratively, at the trial court, and at the Court of Appeal that the project should be denied because it did not comply with several General Plan and Community Plan guidelines that call for contextual development and massing moderation of tall towers. They also argued that the City should not approve waivers that contradicted the guidelines, and that the City should have approved a shorter and squatter development that had the same number of units but a smaller courtyard.

The Court began its analysis by noting that the neighbors had “sidestepped” the implications of the DBL, not discussing it at all in its opening brief and then dismissively claiming the DBL is not a “free pass.” The Court identified the narrow grounds by which a City can shrink or deny a DBL project and pointed out that the neighbors simply failed to make any arguments about that point.

It then went on to explain that the developer specifically requested concessions under the DBL that were germane to each of the General Plan and Community Plan guidelines the neighbors claimed the project did not comply with. The City Council expressly made a finding that there was no evidence to support the denial of the requested incentive, which the Court found to be determinative—acknowledging that the burden on this issue has now shifted to cities if they attempt to deny a project, not the developer proposing an incentive. It also concluded that the project’s waivers were correctly layered on top of the project with requested concessions, meaning a project qualifies for waivers based on its form with both the density bonus and the concessions.

The Court finally rejected the neighbors’ claim that the project’s design was not dictated by the density bonus and concessions, but by a large courtyard. It pointed out that this precise argument was raised and rejected in the Wollmer v. City of Berkeley case from 2011, one of the first cases analyzing the modern DBL. The San Diego City Council could not demand the developer remove the courtyard or redesign its building to satisfy the neighbors’ subjective concerns. The Court stated: “a city cannot apply a development standard that would physically preclude construction of the project as designed, even if the building includes ‘amenities’ beyond the bare minimum of building components.” It remains to be seen what qualifies as an “amenity” that can be baked into a project other than a courtyard, as both Wollmer and the San Diego case related to open space and courtyard amenities. And the evidentiary burden and procedural posture here were also the same as Wollmer: a city defending a project approval with amenities instead of making a project shorter or smaller by eliminating them. This issue may be ripe for further litigation.

The Newark case—Citizens Committee to Complete the Refuge v. City of Newark et al. (2022) ___ Cal.App. ___ (A162045, Alameda County Superior Court No. RG19046938)—and the San Diego case—Bankers Hill 150 et al v. City of San Diego et al (2022) ___ Cal.App. ___ (D077963, Super. Ct. No. 37-2019- 00020725-CU-WM-CTL)—are reminders that well-crafted CEQA documents, entitlement applications, and approval motions can help ensure new state laws meant to protect and streamline housing projects are accurately applied to a project.

 

Authored by Reuben, Junius & Rose, LLP Attorney Mark Loper.

The issues discussed in this update are not intended to be legal advice and no attorney-client relationship is established with the recipient.  Readers should consult with legal counsel before relying on any of the information contained herein.  Reuben, Junius & Rose, LLP is a full service real estate law firm.  We specialize in land use, development and entitlement law.  We also provide a wide range of transactional services, including leasing, acquisitions and sales, formation of limited liability companies and other entities, lending/workout assistance, subdivision and condominium work.

Plan Updates in Oakland and SF

Downtown Plan

This week, we discuss Oakland’s most recent status report on its proposed Downtown Specific Plan and San Francisco’s kickoff of its own General Plan update.

Oakland’s Downtown Plan Progresses, with Changes

Oakland’s sixth area plan—and the first to focus exclusively on the downtown area—is moving forward again, but with modifications based on feedback provided on the draft Environmental Impact Report (“Draft EIR”) and in response to Covid’s impacts on urban life, including efforts to address the City’s acute housing shortage and homelessness and affordability crisis. The City now anticipates City Council review of the Plan by the end of the calendar year.

The Downtown Oakland Specific Plan (“DSOP” or “Plan”) has been in the works since the mid-2010s. The Plan and accompanying Draft EIR were published in August 2019; they envisioned and evaluated 29,100 new residential units, approximately 17 million square feet of office, nearly 2.5 million square feet of retail, and over 1 million square feet of “flex” commercial and industrial space. It covers many different neighborhoods and districts in downtown, including Kono, Uptown, San Pablo, the “central core” of Downtown, Lakeside, Old Oakland, Jack London and the surrounding area south of I-880, and Laney College.

The City’s brief summary update a few weeks ago explains that changes to the Plan’s proposed zoning controls will “address the changing nature of retail” presumably brought on (or exacerbated, depending on your perspective) by the pandemic, identify and regulate priority areas for arts and institutional cultural uses, and encourage increased development in exchange for enhanced community benefits. This voluntary “Zoning Incentive Program” as proposed will set clear metrics for public benefits necessary to achieve enhanced density, such as affordable housing, reduced rent for non-profits and arts organizations, and homelessness services.

Oakland is also undertaking a study on options to fund more housing. These include potential new or increased impact fees, an inclusionary housing requirement that could be more robust than the City’s current policies, and infrastructure financing.

The City anticipates three more phases of planning before the Project and accompanying environmental review are considered by Council: first, revising the DSOP, responding to comments on the Draft EIR, drafting new zoning regulations, and analyzing housing funding options in the Winter and Spring of 2021; next, completing the revised DSOP, responding to EIR comments, completing the housing funding analysis and updated zoning regulations in the Spring and Summer of 2021; and finally, holding adoption hearings on the final DSOP, EIR, zoning amendments, and housing funding program in the Fall and Winter of 2021.

Reuben, Junius, & Rose LLP has experience with entitlement projects and land use diligence throughout Oakland, and we are pleased to have worked on some of the largest housing projects approved in the city over the last several years. We will continue to track this significant rezoning and community planning effort as it moves forward.

San Francisco Kicks Off General Plan Update

Later this month, the San Francisco Planning Department will hold a series of virtual public meetings kicking off an update to San Francisco’s General Plan. 12 meetings are scheduled to run from March 15-26. City staff will discuss topics such as housing, transportation, climate resilience, environmental justice, and racial and social equity. The introductory session is set for Monday, March 15, and one or two events per day focusing on a specific aspect of the General Plan will follow. We are monitoring the update closely and will keep you up to speed as the City releases more information.

 

Authored by Reuben, Junius & Rose, LLP Attorney Mark Loper.

The issues discussed in this update are not intended to be legal advice and no attorney-client relationship is established with the recipient.  Readers should consult with legal counsel before relying on any of the information contained herein.  Reuben, Junius & Rose, LLP is a full service real estate law firm.  We specialize in land use, development and entitlement law.  We also provide a wide range of transactional services, including leasing, acquisitions and sales, formation of limited liability companies and other entities, lending/workout assistance, subdivision and condominium work.